The rebuilds of PPL’s Berks–Lavino 69 kV and South Akron-Millwood-Strasburg 230 kV lines in Pennsylvania represent a good example of how transmission investment can potentially reshape congestion patterns and price formation in PJM.
From 2020 through 2025, the BOONETWN–SREADING BOO-SRE A 230 kV, Real Time constraint (all contingencies) showed persistent and, at times, extreme congestion costs. Following the completion of both line projects in September 2025, the constraint appears to have stopped binding.
This case highlights:
How transmission projects evolve over time
Strong candidate scenarios for power flow modeling
The direct link between grid topology changes with congestion trading opportunities and risk mitigation
How Yes Energy’s tools can give you both a leading indicator and a real-time confirmation of grid changes affecting congestion
For power traders and utilities, changes in transmission, generation, and load infrastructure are among the most powerful and underutilized sources of market edge.
Tracking projects like the Berks–Lavino and South Akron-Millwood-Strasburg line upgrades are not straightforward:
Fragmented data sources: Information is spread across PJM planning reports, PUCT filings, construction queues, and utility reports
Constant revisions: In service dates shift and scopes change
Long timelines with uncertainty: Projects can take 2–10+ years, with multiple false signals or changes along the way
Nonlinear market impact: A project may have zero impact—until the day it goes in service and alleviates a multi-million-dollar constraint or changes power flow in the area
Topology complexity: Understanding why it is important to consider transmission projects in a sensitive area with many historical constraints and contingency pairs requires careful examination, and ideally, a power flow model
Despite the complexity, the payoff is enormous:
Forward congestion forecasting: Anticipate places where constraints could persist, disappear entirely, or even move down the line
FTR and congestion strategy alignment: Avoid holding positions that are structurally at risk of collapse, or have the opportunity to reduce risk
Fundamental price modeling: Incorporate real grid changes rather than relying solely on historical patterns
Utility planning & risk management: Understand how upgrades affect reliability, flows, and exposure to congestion costs
At Yes Energy, we recognize how time-consuming it can be to efficiently track the ever-evolving power grid.
That’s why our dedicated Infrastructure Insights team is focused exclusively on energy infrastructure project tracking:
Continuous monitoring of PJM and other ISOs across North America
Normalization of messy, evolving project data
Tracking of ISD changes and scope adjustments throughout the development cycle
Project probability scores to filter out the noise
Infrastructure Insights transforms raw data from hundreds of different data sources into actionable intelligence—giving our clients clarity on when and how the market will change.
The BOONETWN–SREADING BOO-SRE A 230 kV constraint was a binding constraint in eastern PJM from 2020 to 2025, most notably under the Lauschtown T3 contingency. While factors such as weather, generation, and transmission outages played a role, two transmission projects highlighted in Infrastructure Insight, Berks–Lavino 69 kV and South Akron–Millwood–Strasburg 230 kV line rebuilds, stand out as key drivers.
Historically active with several different contingencies, the constraint shows a clear seasonal summer pattern but disappears entirely after September 2025. The timing suggests a strong relationship with the completion of these line rebuilds, as the constraint has not bound in real time for seven consecutive months.
Figure 3: Real Time hourly LMP spread between BERKS 69 KV BUS_1 and BIRDBORO 23 KV AUX2 on September 25th, 2025, HE20 on one of the last times the constraint was binding.
This behavior reflects:
Overload on BOONETWN–SREADING BOO-SRE A 230 kV for the loss of LAUSCHTOWN T3 230/500 kV
Limited paths for power delivery to Reading, PA and Lancaster, PA areas
Utility: PPL
Scope: Rebuild the Berks–Lavino 69 kV line
Timeline: Announced 2015, Under Construction late 2024/early 2025, Operating September 2025
Figure 4: Infrastructure Insights view of the Berks-Lavino 69 kV Line Upgrade.
Utility: PPL
Scope: Rebuild the South Akron-Millwood-Strasburg 230 kV line
Timeline: Announced 2020, Under Construction early 2025, Operating September 2025
Once the rebuilds are energized and in service, the constraint appears to be alleviated. However, the BOONETWN–SREADING BOO-SRE A 230 kV real-time constraint has historically been most active during hot weather conditions. Although the addition of two new lines is expected to improve power delivery to high-demand areas, the true test will come under high load in the coming months. That said, such upgrades can shift congestion elsewhere, potentially creating new bottlenecks—especially in areas where infrastructure is aging or has been compromised, as seen with the Berks–Lavino 69 kV line following fire damage.
Persistent congestion with high volatility
Repeatable seasonal spikes
Strong driver of nodal price separation
Congestion appears to be alleviated on the constraint
2026 summer months will test this theory
1. Infrastructure Changes Drive Structural Market Shifts
This was not noise; it was a permanent change in price formation.
2. Identifying Projects is Easy—Tracking Them Accurately and on Time is the Real Challenge
Timelines change repeatedly
Scope evolves
Time spent trading vs gathering data
Market impacts are not obvious without tools, such as PowerSignals®, to conduct deep analysis
3. Dedicated Tracking Is a Competitive Advantage
Without systematic tracking, it’s easy to:
Overestimate congestion persistence
Miss-timing on position unwinds
Hold long-dated positions that are structurally at risk of collapse
The Berks–Lavino and the South Akron-Milwood-Strasburg rebuilds demonstrate how transmission projects can affect a long-standing congestion opportunity and, in turn, trading decisions and risk mitigation.
In today’s markets, where infrastructure is rapidly evolving, the ability to:
Track projects accurately
Interpret their system impact
Translate that into market outcomes
…is no longer optional—it’s a core competency.
With Infrastructure Insights as a starting point and in-house power flow models to confirm your assumptions, Yes Energy provides the tools to turn complex, fragmented infrastructure data into clear, actionable insight for traders and utilities.